S.NO. Discription of work Project name client name Project management consultant (PMC) Value of work Date of Award Remark
1 Construction and sinking of RCC
Circular well of 6.5 meters
and 4.5 meters internal dia
DJB Sewer project package-05 DSC Limited Engineers india Limited (EIL) 53,188,100 29.02.2012 Completed
2 j Hanger installation work Mumbai project ABB Limited ABB Limited 561,800 10.09.2012 Completed
3 Micro Tunnelling work by using pipe jacking method Micro Tunnelling sewer project Tactic Tunnelling company pvt. ltd. Engineers india Limited 21,500,000 13.03.2013 Completed
4 Rectification work at Package-5 DJB Srewer project Package-5 DSC Limited Engineers india Limited (EIL) 1,000,000 01.05.2013 Completed
5 Rectification work by sleeve pushing and RCC pipe jointing at Package-5 DJB Srewer project Package-05 DSC Limited Engineers india Limited (EIL) 700,660 13.07.2013 Completed
6 Rectification work at Package-4 DJB Srewer project Package-04 DSC Limited Engineers india Limited (EIL) 600,000 17.07.2013 Completed
7 RRC pipe cutting work at Package-5 DJB Srewer project Package-05 DFW Engineers india Limited (EIL) 75,000 30.09.2013 Completed
8 Trenchless pipe pushing work (HDD work) at Shahdra DJB Interceptor SPS P-5 VA Tech Webag Limited VA Tech Webag Limited 421,350 27.11.2013 Completed
9 Retrival MTBM, Rescu work at Package-05 DJB Sewer Project Package-05 DFW Engineers India Limited (EIL) 781,794 25.01.2014 Completed
10 Sheet pilling retrival work at Vindhya Nagar NTPC, MP Sheet Pilling Retrival JMC NTPC 3,000,000 22.04.2014 Completed
11 Prividing, Laying, Joining, Testing and commissioning and allied works of Secondary Sewerage to connect the Secondary Sewerage Outfalls discharging (group -02) IMC sewer project EMS-Himal hydro JV SGS 1,11,60,000 04.02.2016 completed
12 Prividing, Laying, Joining, Testing and commissioning and allied works of Secondary Sewerage to connect the Secondary Sewerage Outfalls discharging (group-02) IMC sewer project EMS-Himal hydro JV SGS 2,40,00000 28.02.2015 completed
13 Laying, Jointing and pushing of 1700MM dia, 1500mm dia, 1200mm dia MS pipe by trenchless technology 53.5 MGD sewage (DJB) pumping station SPML Infra limited 27,25000 04.11.2014 completed
14 extraction of soidler pile at B.C.P. with vibro hammer and lifting it with cran design and contstruction of tunnel DMRC FEMC- pratibha JV 30,00000 23.09.2014 completed
15 1200 MM dia micro tunnelling work by using pipe jacking mathod with micro tunnelling boring matchine DJV sewer project package-4 DSC EIL 4,90,00000 22.02.2013 40% complete / delay by client
16 Prividing, Laying, Joining, Testing and commissioning and allied works of Secondary Sewerage to connect the Secondary Sewerage Outfalls discharging (group-01) IMC sewer project EMS-Himal hydro JV SGS 82,65,000 14.03.2016 completed
17 1500,1300,1100 MM dia MS pipe by trenchless jack pushing method under railway in hardrock Ban-sugara irrigation scheme project Larsen & Toubro Ltd LTD 81,19,580 24.11.2017 95% completed
18 1200,1000,600 MM dia MS pipe by trenchless jack pushing method underrailway/ National highway / state highway and PWD road IWSS PITHAMPUR Project Larsen & Toubro Ltd LTD 2,29,80,55,000 01.01.2018 60% complete
19 Retrival MTBM, Rescu work at Package-05 DJB Sewer Project Package-05 DFW Engineers India Limited (EIL) 781,794 25.01.2014 Completed